VI. STEAM AND POWER PLANT

1. Boilers:
  • 4 Nos. in all.
  • 1 No. Taxmaco Boiler of 50 Ton capacity w.p. 32 Kg/cm2. complete with forced and induced drought,air heaters, super heaters and bagasse spreader stocker.
  • 2 Nos. 12 Ton cap. B & W Make w.p. 14Kg/cm2, Air heater complete with I.D. and F.D. with economizer, spreader stocker.
  • 1 No. Jhon Thomson make of 17 Ton cap. w.p. 14 Kg/cm2 complete with I.D/.F.D. super heater, economiser, spreader stocker and air heater.
2. Power Plant:
Number of prime movers, : 2 Nos. in all.
1 2
Make T.E.W B.B. Turbine
Power Cap. (KW) 3000 1500
Working Pressure (Kg/sq.cm.) 32 13.7
B.P.Temp°.Cen. 380±15 240
Power factor 0.8 0.8
Alternator Make B.H.E.L. Brown Bovery


VII. GENERAL
FFinal molasses storage tanks, number, type and capacity of each tank:
A. 1 No. M.S.Tanks 15,337 Qtls Cap.
B. 1 No. M.S.Tanks 30,279 Qtls Cap
Pucca Pit –
No.1 - 41691 Qtls.
No.2 - 45502 Qtls.
TOTAL = 133009 Qtls Cap.