VII.
COGENERATION
At Khatauli a Co-generation Plant of 23.0 MW is being installed
| - Boiler
|
- 120 T
|
Capacity
87 Kg M² IJT make : Bagasse fired |
| - Power
Turbine |
- 23.0 MW |
|
VIII.
GENERAL
Final molasses storage tanks, number, type and capacity of each tank:
| A. |
2 Nos. M.S.Tanks
19,000 Qtls Cap. |
| B. |
1 No. M.S.Tanks
22,000 Qtls Cap |
| C. |
1 No. M.S.Tanks
48,000 Qtls Cap |
| D. |
1 No. M.S.Tanks
80,000 Qtls Cap |
| E. |
1 No. M.S.Tanks
1,00,000 Qtls Cap |
| F. |
1 No. M.S.Tanks
60,000 Qtls Cap |
| TOTAL = |
7 Nos. M.S.Tanks
3,48,000 Qtls Cap |